Instructions
Receiving, Handling, and Storing Motor
Control Centers
Receiving
1. Upon delivery of the motor control center, inspect the shipment for lost
items and any damage that may have occurred during transit. If the
package appears to be damaged, it may be necessary to unpack the
equipment and inspect it for further damage.
2. In the event that there is evidence of loss or damage, the buyer must
follow the procedure outlined below:
Note on the delivery receipt that the equipment being received is
damaged.
Contact the carrier that made the delivery and schedule an
inspection.
Inform the local Rockwell Automation representative that the
equipment is damaged.
Retain all product packaging for review by the carrier’s inspector.
For further assistance, contact Rockwell Automation support at (440)
646-5800. Navigate through the call tree by selecting option 2 for
Allen-Bradley products, option 5 for motor control centers, and then option 1
for hardware support.
IMPORTANT
Delivery of equipment from Rockwell Automation to the
carrier is considered delivery to the buyer. The carrier
becomes liable for any damage that occurs during transit. It
is then the buyer’s responsibility to notify the proper party
if damage is found. The buyer may forfeit any right to
recovery for loss or damages by failing to comply with the
following steps.
Vista de pagina 0
1 2 3 4 5 6 ... 11 12

Indice de contenidos

Pagina 1 - Control Centers

1InstructionsReceiving, Handling, and Storing Motor Control CentersReceiving1. Upon delivery of the motor control center, inspect the shipment for los

Pagina 2 - Handling

Publication 2100-IN040B-EN-P - October 200210 Receiving, Handling, and Storing Motor Control Centers

Pagina 3 - Overhead lifting

Publication 2100-IN040B-EN-P - October 2002Receiving, Handling, and Storing Motor Control Centers 11

Pagina 4

Publication 2100-IN040B-EN-P - October 2002

Pagina 5

Publication 2100-IN040B-EN-P - October 20022 Receiving, Handling, and Storing Motor Control Centers HandlingThe following guidelines are

Pagina 6 - Lifting sling

Publication 2100-IN040B-EN-P - October 2002Receiving, Handling, and Storing Motor Control Centers 3Refer to and follow the forklifting pr

Pagina 7 - Rod or pipe rollers

Publication 2100-IN040B-EN-P - October 20024 Receiving, Handling, and Storing Motor Control Centers 1. Attach rigging to lifting means.2.

Pagina 8

Publication 2100-IN040B-EN-P - October 2002Receiving, Handling, and Storing Motor Control Centers 5 Figure 2 Overhead lifting a front moun

Pagina 9

Publication 2100-IN040B-EN-P - October 20026 Receiving, Handling, and Storing Motor Control Centers Lifting slingUsing a lifting sling is

Pagina 10

Publication 2100-IN040B-EN-P - October 2002Receiving, Handling, and Storing Motor Control Centers 7 Figure 5 Lifting sling on NEMA Type 3R

Pagina 11

Publication 2100-IN040B-EN-P - October 20028 Receiving, Handling, and Storing Motor Control Centers Figure 6 Pipe rolling a motor contro

Pagina 12

Publication 2100-IN040B-EN-P - October 2002Receiving, Handling, and Storing Motor Control Centers 9

Comentarios a estos manuales

Sin comentarios