Rockwell-automation FactoryTalk Scheduler Users Guide Manual de usuario Pagina 87

  • Descarga
  • Añadir a mis manuales
  • Imprimir
  • Pagina
    / 146
  • Tabla de contenidos
  • MARCADORES
  • Valorado. / 5. Basado en revisión del cliente
Vista de pagina 86
6 USING FACTORYTALK SCHEDULER
81
• • • • •
Clicking on the Neck Post 2 order causes the operations of the order to be displayed in the
operations section of the window. The initial sequence of the operations is based on the
Op Number. You can re-sequence the order by clicking on any of the operation column
headers. Now double-click on the second operation, Op Number 20, which will open the
Operation Constraints window for that operation, shown below.
Vista de pagina 86
1 2 ... 82 83 84 85 86 87 88 89 90 91 92 ... 145 146

Comentarios a estos manuales

Sin comentarios