Pre-Commissioning
Pre-Commissioning
Responsibilities
Rockwell Automation manages the start-up service for each installed drive at the
customer’s site, but there are a number of tasks the customer or its representatives
must complete before scheduling Rockwell Automation personnel for drive
commissioning.
Review this information prior to commissioning the drive as a reference for drive
line-up commissioning. Record the information in the data sheets provided;
these are useful during future maintenance and troubleshooting exercises.
Inspection and Verification
Before the drive commissioning occurs, Rockwell Automation recommends that
the customer arranges a pre-installation meeting to review:
a. the start-up plan
b. the start-up schedule
c. the drive(s) installation requirements
d. the pre-commissioning checklist
Customer personnel must be on-site to participate in the system start-up
procedures.
See Safety and Codes
on page 41.
ATTENTION: Perform the pre-commissioning tasks in the order listed in this
chapter. Failure to do so may result in equipment failure or personal injury.
IMPORTANT
Rockwell Automation requests a minimum of four weeks’ notice to schedule
each start-up.
ATTENTION: The CMOS devices used on the control circuit boards are
susceptible to damage or destruction by static charges. Personnel working near
static sensitive devices must be appropriately grounded.